Gas Heaters - Beat the Lead Time

Writer's picture: Jerry TybergheinJerry Tyberghein

This unit required a 2000MBH burner, however due to lengthy lead times for higher capacity heaters, we were able to utilize (4) 500MBH burners. Each 1000MBH stack has a single power and 0-10 connection. All burners require individual gas connections.



4 views0 comments